10 Reasons Construction Project falls behind Schedule

10 reasons construction project falls behind schedule

Unfortunately, many construction projects are completed late. Invariably this negatively impacts the contractor’s reputation and costs both the contractor and their customer money. Often the contractor has to pay penalties for finishing late and they incur additional costs to remain longer on the project. The customer receives access to their facility late and usually faces additional costs for supervising the project for a longer period.

A well-prepared schedule that is regularly updated allows us to detect early when a project is running late. When we fall behind, the normal course of action is for the contractor to place more resources on the project or work extended hours in the hope of catching the lost time. Unfortunately, this doesn’t always help as the true cause of the slippage hasn’t been uncovered. In fact, adding more people or resources to the project may even add to congestion making the problem worse – especially if they aren’t the right resources.

Usually, the longer the problem persists the worse the schedule slippage becomes and the less time remains to catch up the lost time.

When schedule slippage is detected it’s important to uncover the real reasons and then take action to rectify the problems. Sometimes the cause may be a minor bottleneck which could be fixed with small adjustments to the running of the project.

Reasons for construction projects falling behind schedule

There are many reasons for a project to finish late. In this blog, I’ll only focus on reasons caused by the contractor. These include:

  1. Material handling on the project site. This is one of the commonest causes of delays in projects. Materials aren’t reaching the area where they’re required. This is a particular problem with multi-story buildings where everything has to be lifted by a crane. Projects often underestimate the number of cranes required, forgetting that trucks have to be off-loaded and that lifting activities don’t happen uniformly throughout the day. Congested project sites can also be a problem delaying deliveries and blocking access routes. What can appear simple on a piece of paper, getting an item from point A to B, is sometimes not so simple on a busy project. Yet often simple steps such as packaging materials differently, having more materials handling equipment, working the lifting equipment longer shifts, changing the sequencing of lifting in the day or more focussed supervision on this activity can unblock this bottleneck and improve production on the whole project. 
  2. Poor productivity. If our labour and equipment aren’t producing what is normally expected we will need extra resources to complete the same amount of work. However, just throwing additional resources at the project doesn’t always yield the desired result and it’s also very costly. It’s often more effective to uncover why productivity is low and try and rectify the problem. Some reasons for poor productivity include:
    • Employees aren’t working their full shifts. They may take an extra five minutes on either side of their tea and meal breaks and leave their workplace up to fifteen minutes early. Before you know it the project is losing between thirty minutes and an hour for every person on every shift.
    • Workers may have low morale due to an underlying problem such as conflict with management or Supervisors, mistakes with their wages, etc. Resolving these problems and improving morale can improve productivity
    • Workers don’t have the right skills. Obviously, a skilled and experienced carpenter will usually produce better quality work faster than someone who isn’t as skilled.
  3. Frequent breakdowns of equipment. Breakdowns of key items of equipment such as cranes, concrete mixing plant, or excavators can cause severe disruption to a project. After suffering innumerable delays on my projects due to crane breakdowns I persuaded the company of the folly and the cost of using old cranes and we embarked on a replacement scheme. Sure new mobile cranes are expensive, but just the increase in productivity on our projects more than compensated for these additional costs. Unfortunately, those studying project schedules don’t always appreciate how disruptive broken equipment can be. Even hiring a better replacement item can change the mood and productivity on the project.
  4. Shortage of materials. This is usually caused by the team not ordering sufficient materials or not allowing for fabrication lead times. Sometimes however the supplier has their own problems and it may be easily resolved by approaching another manufacturer. Even problems with insufficient delivery trucks can disrupt supplies. It could be an easy fix by bringing on other transport companies.
  5. Theft of materials or equipment. In previous articles, I highlighted one project where a third of every load of cement the project received was stolen en route. The project experienced cement shortages which hampered our production and caused delays. Sometimes the theft could be as small as removing a battery from an excavator which, in the countryside, could mean the machine and the other equipment working with it stands for several days. Even the theft of small electrical tools from a tradesman can mean they’re not working efficiently for hours or even days. Unfortunately, theft can create bigger problems particularly if it is a long lead item such as an electrical distribution board.
  6. Having too few resources of a particular trade. I’ve often experienced projects where one trade has held up the others. For instance, if you have insufficient scaffolders you aren’t going to be erecting the scaffolding fast enough for your steel fixers and carpenters so they are going to be standing. If we need more people ensure we get those with the skills we are short of on the project and not just more of everyone. Sometimes there is only a minor hold-up and it may be possible to get the project through by asking a few employees with the required skills to work extended shifts.
  7. Poor quality work resulting in rework. Poor workmanship causes delays when completed work has to be demolished and rebuilt. Even minor rectification work can distract valuable resources away from critical tasks.
  8. The Supervisors and the team doing the work aren’t aware of or don’t understand the schedule. This may seem stupid, yet, this happens surprisingly often. Management may give a copy of the updated schedule to Supervisors but often this is the schedule for the whole project for the remaining duration and it could be several or even hundreds of pages long. Most Supervisors are only concerned with their section of work and what needs to be done in the next couple of weeks. Therefore give them only their relevant sections of the schedule for the next few weeks. In fact I’ve found that, if possible, providing a schedule in a pictorial form highlighting the important dates works well as it can be put up on their office wall and is easily understood by their team. Even better is to spend time explaining to the Supervisor what needs to be achieved and explaining why certain dates are critical to the project. It’s amazing how a team who know what they have to achieve and the reasons behind it can then deliver.
  9. Neighbouring sections of work negatively impact each other. This is usually because of congestion, safety issues or access problems. By analysing these problems sometimes we can develop solutions which may mean using different access systems, bigger cranes, additional safety measures, changing the sequence of the work, or even working different shifts (one section could work the day shift while the other at night). Yes, there may be additional costs, but not falling behind schedule is often more important.
  10. A subcontractor isn’t performing. One non-performing subcontractor can impact other subcontractors and your own team. Often all it takes is the subcontractor to improve their performance, and bring on extra people to stop slippage on the schedule. In extreme cases, you may consider taking work away from the subcontractor. Of course, ensure that your dealings with the subcontractor are in accordance with your contract with them. Also, understand why they aren’t performing as the reasons could be due to your team or the customer’s team. 

Maxx Builders’ Project Delivery Methodology

The difference between a commercial construction project that finishes on time and one that doesn’t is almost always set in the first 30–60 days. Maxx Builders’ delivery methodology focuses on four critical-path items: permits, long-lead materials, finalized finish selections, and constructability review.

Permits in Texas vary materially by jurisdiction. City of Houston Department of Public Works runs different timelines than unincorporated Harris County or City of Sugar Land. We secure preliminary permit consultation during schematic design — not at the end of construction documents — to avoid the typical 4–8 week surprise discovery of a missing review requirement.

Long-lead materials are the second schedule risk. Generator switchgear, custom mechanical equipment, specialty glazing, and brand-prototype FF&E often have 16–32 week lead times. (Per Gordian Q1 2025 supply-chain analysis; BLS PPI) Identifying these during preconstruction and committing orders before final documents protects the schedule.

Owner finish selection is the third common slip point. The pattern: schematic design completes; construction documents start; owner is still selecting finishes through bid; selections lock 4 weeks before construction; key items have 12-week lead time. Result: late material delivery and overtime to recover. Maxx Builders’ preconstruction process locks owner-finish selections by design development.

Constructability review at 50% and 90% CDs catches conflicts (MEP coordination, structural interference, accessibility code gaps) before they become field RFIs. Each in-field RFI costs 8–20 hours of project management time plus potential delay. (AACE International change-cost benchmarks)

If you’re planning a Texas commercial project, our construction management services apply this methodology end-to-end.

From Concept to Certificate of Occupancy: Project Phases

Commercial construction projects in Texas typically run 8–24 months from concept to certificate of occupancy. The phases below describe what happens at each stage and what owners should watch for. Maxx Builders has delivered hundreds of commercial projects through this lifecycle — from a 4,500 sq ft music academy interior build-out to a 243,031 sq ft industrial warehouse. The pacing is similar across project types; the content differs.

Phase 1: Programming & Feasibility (4–12 weeks)

The earliest phase — and the most impactful for total cost. Owner defines program (square footage by use, occupancy load, special requirements). Architect or design-builder produces a programming document with massing, structural grid concept, and site placement. Preconstruction cost estimate at this phase is rough (±15–20%) but anchors feasibility. Geotech investigation should start. Site survey, ALTA if not already done. Zoning verification. Owner secures construction financing letter of intent.

Phase 2: Schematic Design (6–12 weeks)

Architectural concept converts to design intent: floor plans, building elevations, primary structural and MEP concepts. Owner-furnished items identified. Preconstruction cost estimate refines to ±10–15%. Pre-application meetings with city. Brand approval gate (for hospitality and franchise). Owner secures construction loan term sheet.

Phase 3: Design Development (8–14 weeks)

Plans develop to substantial detail: dimensioned floor plans, sections, exterior wall details, MEP system layouts and capacities, finishes specified. Owner-finished selections locked. Long-lead material orders identified. Preconstruction estimate at ±5–10% confidence. Geotech report finalized. Civil and storm-water design.

Phase 4: Construction Documents (8–16 weeks)

Final drawings issued for permit and construction. All trade-coordinated. Bid documents complete. GC final price locked. Construction loan closing. Permit submittal. The transition into the field is the highest-friction window in the project — coordination gaps revealed here cost the most to resolve.

Phase 5: Construction (6–18 months)

Sitework, foundation, structure, envelope, MEP rough-in, finishes, FF&E installation, commissioning. Monthly draw cycle with lender. Inspections at code milestones (foundation, framing, MEP rough, final). Owner monitors progress via OAC meetings and pay applications.

Phase 6: Closeout & Move-In (4–8 weeks)

Punch list completion, final inspections, certificate of occupancy, warranty package, O&M manuals, owner training, FF&E final install. Frequently underestimated phase — closeout typically takes 30% longer than scheduled if not actively managed.

Critical-Path Items by Phase

Within these phases, certain items consistently sit on critical path:

  • Programming → permit strategy (talk to city early)
  • Schematic → geotech (drives foundation type)
  • DD → long-lead material commitments (generator, custom mechanical)
  • CDs → city plan review timelines (8–16 weeks in Houston)
  • Construction → weather windows, especially Texas summer concrete pours
  • Closeout → final inspection scheduling with city

Schedule Risk Mitigation

KPMG’s 2015 Global Construction Survey found only 25% of projects came in within 10% of original deadlines — 75% missed by more (KPMG Global Construction Survey 2015; McKinsey “Reinventing Construction” 2017). Maxx Builders applies three risk-mitigation practices: phase-gated milestone reviews, pull-planning sessions with trade partners, and weekly schedule recovery analysis. Together these target on-time delivery within 5% of contract date on most projects.

Learn about our construction management services or request a project consultation.